Context 

  • The client was running out of warehouse capacity sooner than expected; therefore, a third facility was needed.

  • A short timeline meant that the design needed to maximize capacity and throughput while minimizing new developments.

Objectives

  • Modernize and increase distribution capacity

  • Design a new DC that can satisfy the next 5 years’ operations needs

  • Address higher customer service level requirements

What we delivered

  • Conceptual design: Designed and validated a high-level layout and process with the client. Relevant costs were collected and calculated to form the business case for approval​

  • Detailed design: The details of the layout and operational processes were defined together with other functions to generate a complete implementation plan. The client required a strong PMO to orchestrate and coordinate different functions​

  • Implementation: A detailed implementation and transition plan and project PMO was set up to closely monitor the progress and manage risks or issues during the implementation​

Results

  • Successfully set up an 85,000 sq. mi. multi-floor distribution centre

  • Improved space utilization and throughput significantly

  • Go-live on time and under budget with no business interruptions​​